Project Portfolio

Town Creek Waste Water Treatment Plant – City of Aiken, South Carolina

General Contractor
Person of Contact: Bruce Myers
Phone Number: (803) 642-7610
Project 100% Complete
Installation of pumps into existing system

Third Level Canal – Augusta, Georgia

Compass Environmental / Williams Environmental Subcontractor
Person of Contact: Tim Morrow
Phone Number: (706) 432-4105
Project 95% Complete
Environmental site remediation. Civil construction for Augusta-Richmond County
Contract Amount: $2,106,669.00
Subcontractor: Dixieland Walls, Inc.
Bret Cathy (706) 650-8740
756 Folley Court
Evans, Georgia 30809

Shoppes of Thomson, Thomson, Georgia

Subcontractor to Wyatt Realty Services
Personal of Contact: Bo Murphy
Phone Number: (803) 649-1411
Civil Site Construction
Project 100% Complete 09/30/2002
Contract Amount: $269,425.00
Subcontractor: S. E. Peters
Person of Contact: Sam Peters
Phone Number: (803) 649-1691
P. O. Box 598
Aiken, South Carolina 29802

USDA Forestry Service

General Contractor
Person of Contact: Ms. Margie Yeaton
Phone Number: (803) 725-0239
Project 100% Complete September 30, 2004
Civil Road Maintenance
Contract Amount Approximately $423,000.00
Subcontractors: N/A

US Army Corps of Engineers

Jackson Barricade, Savannah River Site, Aiken, South Carolina
Subcontractor
Person of Contact: Gary McAllister
Phone Number: (803) 952-9185
Civil Construction for the US Army Corps of Engineers
Project 84% Complete
Contract Amount: $281,299.00
Subcontractor: Peek Services Co., LLC
P. O. Box 11437
Columbia, South Carolina 29211
Person of Contact: Doug Wolford
Phone Number: (803) 217-0222

Georgia Department of Transportation

General Contractor
Person of Contact: DOT Contracting Office (404) 656-5325

Baston Road, Martinez, Georgia
Project 100% Complete
Contract Amount $6,560,000.00

Barton Chapel Road, Augusta, Georgia
Project 100% Complete
Contract Amount $2,601,343.00

Washington Rd
Project awarded 12/12/07
Contract Amount $4,033,000.00

Augusta Mall, Augusta, Georgia

General Contractor
Person of Contact: Linda
Phone Number: (706) 733-1001

Dillard’s Department Store Parking Lot Addition-Sitework
Project 100% Complete
Contract Amount $2,000,000.00

Storm Sewer Renovation
Project 100% Complete
Contract Amount $1,800,000.00

VCC

Person of Contact: Rick Sanzs
Phone # 770-225-1900 Utilities/Site Work
Contract Amount $4,639,215.00

CR Myers

Person of Contact: Joe Augustine
Phone # 920-379-5182
Site Work, Utilities Process Piping and Railroad Work
Contract $12,800,000.00
Completed on schedule (fast track schedule)

Columbia County

Person of Contact: George McDavid, One Source Development
Blackstone Camp (Middle School)
Phone # 706-863-8010
Completed 95%
Contract Amount $ 3,427,802.10
Worked Performed Site Work, Utilities, Concrete

Fort Gordon

Person of Contact: Arnold Brannon
Law Enforcement Center
NSA Building
BattleLab
Completed 85%
Contract Amount 3,200,000.00
Worked Performed Site Work, Utilities, Concrete, Building